Power Requirements
One 220 Volt, 50-amp circuit for each truck,
accessible within 100' cord length, dedicated to our
use during our work. We will hook up to the panel,
if requested; if not, we will not be responsible for
delays if the project electrician cannot install our
pig tail in a timely manner.
Trucks on site overnight will have to remain
connected to power (at least one 100-volt circuit)
in cold weather to prevent damage to the foam
product raw materials and our equipment.
If you wish to have us supply our own power, we
will arrange for a generator for an additional cost
of $75 for the first day of each mobilization
and $95.00 for each subsequent day. In small areas
or remote locations, we may elect to use small-scale